|

August
2006
The Heat is on the Grid
By Ken Silverstein, Editor-in-Chief,
EnergyBiz Insider
When the heat is on, the transmission grid is
tested. And it passed without serious incident during the
unseasonably hot temperatures in mid July. But, reserve margins in
some parts of the United States took a dip, emphasizing the need for
new and modern forms of generation that can be sent over a robust
transmission system.
The recent spate of hot weather is only a reminder
of a much broader debate — the need for more investment in the
North American grid. The energy law that passed in 2005 sets out to
force utilities and other transmission owners to comply with
mandatory rules to ensure more reliability. Federal regulators,
meanwhile, are working to establish incentive-based rates and using
its newfound backstop permitting authority.
Last week, Ontario, Canada almost broke through its
previous peak usage, generating about 26,000 megawatts, while
Philadelphia-based PECO surpassed its previous all-time high peak
set a year ago, using roughly 8,600 megawatts. President Denis
O'Brien said the local distribution system performed very well under
the extreme heat and unprecedented demand. "Our customers depend on
us to provide reliable power when they need it the most, and PECO
came through, once again."
The whole scenario stresses the need for ample
reserves, or surplus power to meet unusually high demand.
Nationally, in the United States, reserves during the heat wave fell
to 15 percent. While acceptable, it doesn't allow much room for
economic growth.
To plan, the Federal Energy Regulatory Commission (FERC) is
now authorized to ensure new "reliability standards." Generally,
that entails motivating investors to put up the capital needed to
expand the transmission system. Toward that end, utilities would be
able to recapture their investments at a faster rate. FERC also has
the ability now to establish national corridors where transmission
is sorely needed.
Transmission investment has declined in real terms
— adjusted for inflation — from 1975 to 1998. While there have
been increases since 1998, FERC says that the level is still less
than what was invested in 1975. Over the same time period, however,
the demand for electricity has doubled. That's resulted in a
significant decrease in transmission capacity, requiring new lines
get built.
"Under-investment is a national problem," says
FERC Chairman Joe Kelliher. "The commission proposes a national
solution that encourages investment in all regions of the country."
The incentives apply to regional transmission organizations (RTOs),
traditional utilities and to transcos, or those that operate
transmission lines but do not own any generation.
Optimal Investment
The PJM Interconnection, which is an RTO that serves
51 million people in 13 states and the District of Columbia, is
progressive. Its board just approved a 15-year blueprint to
construct $1.3 billion in electric transmission upgrades. That
includes a 240-mile, 500-kilovolt transmission line from
southwestern Pennsylvania to Virginia to be constructed by Allegheny
Power and Dominion.
The total plan upgrades are expected to provide grid
reliability through 2011 and are estimated to reduce congestion
costs by $200 million to $300 million annually. To meet long-term
needs through 2021, the RTO is looking at 10 other transmission
lines totaling $10 billion, including the high-voltage transmission
line projects proposed by American Electric Power, Allegheny Power
and Pepco Holdings. Transmission owners for these projects have been
authorized to begin the permitting process and undergo environmental
impact assessments as well as potential right-of-way acquisitions.
All told, PJM has authorized more than $4 billion of
accumulated transmission investment since its planning process began
six years ago, resulting in an additional 18,717 megawatts of new
generation being interconnected, with 3,777 megawatts of generation
now under construction. More than $500 million in transmission
projects have been completed.
"Regional transmission planning works," said Audrey
Zibelman, PJM's executive vice president and chief operating
officer. "It's stimulating the necessary investments in the grid to
maintain reliability and to improve economic efficiency." She adds
that the planning process has evolved from one that focuses on
upgrades to one that concentrates on the long-term and better
addresses economic efficiency and major transmission additions.
Elsewhere, four governors of Western states have
given their support to building 1,300 miles of power lines at
a cost of $2 billion. If the projects are constructed and begin
delivering electricity by 2011, lines would stretch from Wyoming
into Utah, Nevada and Southern California. The governors say that
the new lines are essential, noting that the demand for power has
risen by 60 percent in the last 20 years but the region's
transmission system has only grown by 20 percent.
Certainly, the average age of assets along with a
growing demand for power and limited capital have combined and sent
warning shots across the bow of the American people and their
elected representatives. The 2003 Blackout, for instance, is said to
have cost anywhere between $4 billion and $10 billion, which
includes not only direct losses but also indirect ones such as those
tied to lost opportunities.
Industry experts say that the optimal investment in
the grid would be $100 billion, paid out in equal installments over
10 years. Progressive technologies exist that would enhance the
system and bring it in line with a high-tech society. But
transmission lines compete with other capital-intensive projects for
money. With a new set of federal rules on the books, the hope is
that such transmission projects will attract new investment and help
usher the nation's energy infrastructure into the 21st century.

Republished with permission from CyberTech, Inc.
EnergyBiz Insider is
published three days a week by Energy Central. For more information
about Energy Central, or to subscribe to EnergyBiz Insider, other
e-newsletters and EnergyBiz magazine, please go to
http://www.energycentral.com/
|