|
Katrina
Poses Extreme Challenges for Power Engineers
by Greg Hill
IEEE-USA Today's Engineer
asked two electric power engineers experienced with storm damage and
service restoration for their thoughts on the devastating
effects of Hurricane Katrina, and what power engineers are
doing, and will need to do, to restore electric service in
affected areas, returning Gulf Coast residents to some semblance
of normalcy.
With flood waters expected to
remain for 30 days or more in New Orleans, drying out power
plants and substations and repairing damage inflicted by the
brackish waters will be priority number one for local utilities.
The recovery process is expected to be slow across the entire
region, and power has been restored to only a small fraction of
consumers. According to its
online emergency center,
Entergy Corporation continues to assess damages, and, as of 2
September, it had restored power to 363,000 of its customers in
Mississippi and Louisiana — but approximately 728,000 remained
without electrical service. Crews are working to restore power
to critical infrastructure — including hospitals and water
treatment plants — before they will be able to turn their
efforts toward restoring residential service.
As the lead federal agency
responsible for energy assurance, the U.S. Department of
Energy's Office of Electricity, Delivery and Energy Reliability
(OE) is working with the Federal Emergency Management Agency and
state and local governments to respond to Hurricane Katrina's
aftermath. OE is posting on their Web site periodic situation
reports outlining progress and challenges. For more, visit:
www.ea.doe.gov/hurricanes.html.
About the Experts
Harold Adams is director of
electric market policy at Dominion Resources Services in Glen
Allen, Va. He has served as manager of Dominion Virginia Power's
control center and later managed the company's storm center.
Both roles involved emergency planning for hurricanes and other
service disruptions. He is a member of IEEE-USA's Energy Policy
Committee and past chair of the IEEE Richmond Section.
Jack Casazza is president of the
American Education Institute in Springfield, Va. He was formerly a
corporate
officer for PSE&G and an executive with major consulting firms.
He is versed in the technical, institutional and regulatory
aspects of energy systems, and has been involved in system
restorations after major hurricanes and ice storms.
Casazza has qualified to work as a utility lineman. He is an IEEE
Life Fellow, and a member and former chair of IEEE-USA's Energy Policy Committee.
----------
TE: What's it like right now
for the power engineers at the utility companies in New Orleans
and along the Gulf Coast?
Adams: Situations like
this present a major challenge. Obviously, the volume of work is
very high and there is usually limited information available
during the initial stages of restoration, making it difficult to understand the
full scope of the job at hand, and to set priorities.
Casazza:
Engineers are trying to do their
job. They have to get out there, they have to supervise and they
have to coordinate.
Almost every company, every
organization has a written plan of how they’re going to handle
all kinds of emergencies. Engineers prepare those in advance;
they try to anticipate what’s going to happen and how it should
be handled.
The first thing they have to do
is assess the situation. What’s the situation with the power
plants and the substations? You have to take a look at your
transmission lines. Part of the question of deciding how to
proceed is can I get crews in? Where are the roads open so
I can get people in? Do I have to fly these people in by
helicopter to do this work? Do I have to get them in by boat? Do
I need help from other companies?
In many cases, people who are in
the engineering department, the planning department, maybe even in the
communications department, if they have a practical background,
[they] will
be given assignments in the field. They’ll be asked to go out
and take a look at how deep the water is; to determine if we can
reenergize some transformers, if we can get an energized
transmission line in? What spare parts will be needed? That’s the kind of thing they're doing and
reporting back. Almost everybody who has some technical
expertise will be given some kind of an assignment in this kind
of situation.
The problem down there with the
hurricane is the difficulty with transportation. If you have a
tornado, the roads are usually open, or at least there’s a way
to get around the fallen things. With this kind of thing,
getting people in there is going to be very, very difficult. But
you have to get people in to take a look at it with their own
eyes, so they can come back and say, “here’s what I think can be
done.” In many cases, there just aren’t enough people to do
this. You have to use everybody you have available in the
office. And get outside help.
----------
TE: What roles do power
engineers assume when a major storm or other natural disaster
strikes, and in the aftermath?
Adams: Power engineers
take on a variety of roles, depending on their specific skills
and experience. In regional power control centers, engineers
must understand the condition of the system and establish
restoration priorities and the sequence for switching to bring
the transmission system back into service. This may involve both
operating judgment and power system modeling to assure the
system remains in a stable state as components are restored.
In local control centers, the
work is similar to the regional centers, but focused on the
distribution system. No distribution service can be established
until transmission is restored to the distribution substations,
so the local centers must work with the regional center. Once
transmission is established, local engineers and operating
personnel can assess damage and establish restoration
priorities. The highest priority generally goes to public
facilities such as hospitals and water treatment facilities, but
the exact sequence will depend upon the extent of damage to both
the electric system and customer
equipment. Obviously, not much can
happen electrically until water recedes. There's really not much
point restoring power early on to areas where customers can't
use it, so work needs to be coordinated.
Some power engineers in either
type of control center may help provide information to media or regulators to make sure the public is
informed of restoration progress.
Power engineers in planning
departments may need to perform analysis related to
restoration or reconstruction of damaged facilities. In some
cases, the system may be reconfigured by installing temporary
facilities, and these often need to be analyzed.
And power engineers are often
called upon to assess the condition of specific pieces of
equipment that may have been damaged or to perform design or
project management for the restoration.
----------
TE: What kind of challenges
does a hurricane like Katrina pose for the generating plants and
the regional/national electric grid, as well as localized
electrical service?
Adams: Generating plants typically
operate under the direction of regional control centers. Their
main priority in an emergency is to make sure that they are in a
condition to run if called upon. Because the transmission system
may have been damaged and the normal customer load pattern
disrupted, flexibility of operation is a key. The main challenge
for a plant, then, is to assess and repair any damage that
may have occurred, and work with the regional control center to
support restoration of service. Plants may also experience
disruption of fuel supply, so this could also be a problem at
some plants.
Under normal conditions, the
regional electric grid is stressed most during periods of high
loads. After damage from a hurricane, load is lost, so the
problems are different. Individual pieces of the network have been damaged and rendered inoperable. The challenge at this
time is to figure out what pieces are left, put them back
together in a sequence that restores as much power as possible,
as fast as possible, and that remains stable in operation as
conditions change and load is added back to the system.
The challenge to localized
service is similar, but there is more detailed focus on the
particular restoration priorities for local customers and
government.
In all of these cases, manpower
and equipment logistics often present a major challenge. The
situation with Katrina looks unprecedented in that respect.
Casazza: As far as the
generating plants go, there can be a lot of damage in the switch
yard. Flying debris can short out pieces of the bus, causing it
to trip out. And you can’t restore anything until you get that
cleaned up. Then you’ve got the problem with the water. If the
water gets too high in a power plant, you’ve got to shut it
down. The same thing is true with a substation. You’ve got to
shut it down before it flashes over. The water will cause it to
flash over and do a lot more damage. The arc will burn things
up. So you shut it down before that happens; and then after the
water goes back, you try to dry it out and restore it.
The grid is probably not existing
too much down there. I don’t know how many transmission lines
they’ve lost, but I know they’ve lost a lot. This is what the
people in the operating center, the dispatch center, have to be
assessing. They have to be assessing it in each of the of the
power pool headquarters, the regional grids, the Regional
Transmission Organizations and Independent System Operators —
they have to be assessing what the situation is.
The first questions that come up
in the dispatch center are: how much generation have we lost?
And how much load (consumers) have we lost? If you’ve lost a lot
more generation than consumers, you probably want to get the
generation started up again and operating and then reconnected
to the system with the transmission lines.
With generating plants and the
national grid, that’s all decided in the control center, based
on information from outside. With individual distribution lines
— the lines that run up and down the streets, that feed into
your house and mine — there’s a tremendous amount of work there
that has to be done.
The first phase is collecting all
of this information, looking at what you can do and how best to
do it? It’s judgment. You may have an advanced battle plan, but
you still have to have a lot of judgment to do it. It’s nobody
else but the engineers, who have worked in this stuff day in and
day out, who have the judgment to do this.
----------
TE: What can be done to make
electrical transmission and distribution systems more robust and
resilient to storms such as Katrina?
Adams: The robustness of
electrical systems under severe weather conditions typically is
a function of several key factors:
1. Design Criteria — Power lines
and other facilities must be designed to withstand the wind
loads expected in a particular geographic area. The
National Electric
Safety Code includes such
construction standards, but in some cases more extreme design
cases are considered by
engineers. Designing for more extreme weather adds cost, but
having strong designs can be critical.
2. Good Maintenance — Once
properly designed facilities are in place, they must be
maintained in a way that preserves their physical and electrical
integrity over the life of the equipment. Poorly maintained
equipment is generally subject to more damage from extreme
conditions, and is less reliable under stress as service is being
restored.
3. Vegetation Management — Much
of the damage during major storms is due to trees or limbs
falling into power lines. While it is unreasonable to expect
that all trees can be kept out of power lines during a
hurricane, damage can be minimized if a well organized tree
trimming program is
maintained. No amount of tree trimming can protect against storm
surge or flying debris along the coast with a storm like
Katrina, but it's also important further inland to minimize
damage from the high winds.
4. Equipment Redundancy — Using
networked circuit arrangements and ensuring spare equipment is
available can help to minimize restoration times. The specific
plans that are reliable and cost effective at each utility will
depend upon local conditions and
requirements. Engineers usually
consider this in the planning process.
Even with all these steps, it's very
difficult to protect systems fully against storm surge, flooding
and flying debris. Service disruption is almost inevitable under
such extreme conditions, but taking the steps above can help
also make it easier to get the lights back on.
Casazza: One of the things
that is essential is planning a transmission system — deciding
what lines should be built and what lines should not be built.
In designing a power system, the transmission engineer should
have in the back of his or her mind: "There are going to be
emergencies of this type; and I’ve got to build a system not just
for normal conditions, but I’ve got to build a system that can
cope with emergencies."
I went through an exercise such
as this when I worked in New Jersey, at Public Service
Electric & Gas (PSE&G). It was a major wind and ice storm around
Thanksgiving, which took down a lot of the distribution circuits
in New Jersey. People were without service for as much as a
week. The net effect of this was that the company said: “We want
to embark on a program to storm-proof all of our distribution
circuits. So, no matter what happens, we can restore service in
two days.” So, they went around and rebuilt a lot of their
circuits, where they put in a steel messenger
to hold up the phased wires, using special types of spacer cable.
They rebuilt a lot of it, and it cost many millions of dollars. And
it was somewhat effective. They’ve had some other
problems with it, but there are some techniques for storm-proofing distribution circuits.
As far as storm-proofing the
transmission circuits is concerned, since the vast bulk of them
have to be overhead, there’s really not much you can do. There
are some ways to put dampers on them so they don’t
bounce as much in a wind. But you really cannot storm-proof the system
completely. No matter what you do, the electric power system is
going to be subject to interruptions — major interruptions.
At one point, the Rockefeller
Commission did a famous study about putting all of distribution
circuits underground. And they came back saying it’s just not
economically feasible. Some people still argue for putting them
underground. But even underground, with the kind of flooding
you’ve got [in New Orleans], you could have problems.
----------
TE: In a storm or disaster
situation, any safety tips for individuals dealing with
electrical outages and downed services?
Adams: Assume that all
downed wires are energized. Don't touch or go near them. Call
the utility or notify police or fire if you see downed wires.
Be patient. Things are bad
enough, don't make them worse. Impatience sometimes leads
people to jury-rig electrical connections or other
equipment. These arrangements can often be dangerous. Don't do
it. Rely on the professionals to get service restored.
There may have already been deaths
from carbon monoxide from running generators, so if you're going
to use a generator, make sure there's ventilation and no wiring
or connections in the high water.
Casazza: Don’t touch
downed wires. Never touch anything. Leave it up to the utility
to take a look at it. If you see a wire draped over a bush,
don’t go over and take it off the bush. If you see something
else lying on the ground, a piece of equipment, don’t touch it.
Leave it alone. Call the utility to come out and take care of
it.
----------

Greg Hill is managing
editors of Today's Engineer online, and can be reach at
g.hill@ieee.org.
|