|
Reengineering for More Reliable Power Distribution
by Mark B. Lively
Restructuring is sweeping the
electricity industry around the world, changing the role engineers must play in achieving a
reliable electricity supply. Previously, engineers designed
and operated “vertically” integrated systems, where the only
interface was the smallish connection associated with the sale
of electricity to customers. Sometimes the customer was the end
user, and occasionally, a distribution utility. But,
except for minor events on the other side of the meter, a single
engineering group was responsible for the reliability of the
vast majority of the system.
Dealing with New Interfaces
Restructuring has created a
jumble of interfaces. Each interface implies that a different
group of engineers is responsible for reliability on either side
of that interface. These interfaces separate not only
engineering responsibility; they also separate financial
responsibility. Different people own the wires on each side of
the meter. Accordingly, we need a way to coordinate not only the
reliability on each side of the meter, but the ownership of the
electricity flowing across the meter. This sort of coordination requires an
appropriate price, tariff or contract for the flow through the
meter.
The flows through the meters on a
vertically integrated utility followed predictable load patterns
and predictable reliability issues. The jumble of interfaces has
created a multitude of non-standard flows across that jumble of
interfaces. The non-standard flows have created new reliability
issues and new pricing issues, issues that are best handled
together. Pricing issues and reliability issues should be linked
together, since that will result in improved network
reliability.
When developing prices for
today's complicated, non-standard flows, engineers need to explain to
financial types the physics behind the non-standard flows across
these financial interfaces, so that there is appropriate
financial compensation. The need for engineers to be educators
is especially true in regard to reactive power.
Competition a Reality
Until the passage of the Public
Utility Regulatory Practices Act (PURPA) in 1978, electric
utilities operated under the myth that they were in a
“vertically” integrated industry with no competition. But the
competition was really there, just not in conventional forms:
- On an esoteric level,
competition exists when two generators are connected in
parallel, even when owned by the same economic interest. The
two generators compete in economic dispatch to meet the
available demand.
- Some factories chose plant
sites based on the utility serving the area.
- Some customers, not just
distribution utilities, chose to generate their own
electricity, e.g., cogeneration. (Yes, cogeneration was used
before the passage of PURPA. Cogeneration just operated in a
more difficult regulatory environment.)
- Competition also existed in
real time, in that neighboring utilities would buy and sell
electricity to each other.
Years ago, economies of scale led
to horizontal integration. The resulting configuration prompted
the boast that the North American electric system is the largest
machine in the world, a machine whose parts compete with each
other.
Automation for Simplification
Horizontal sales have
occurred since the first interconnection, but the transactions were not automated, except in some power pools such
as the Pennsylvania New Jersey-Maryland integrated power pool
and the New England Power Pool, or within holding
companies such as American Electric Power, Southern Companies,
and MiddleSouth Utilities (now Entergy Corporation.) Instead,
each transaction was custom tailored. PURPA also allowed industrial cogeneration to hook to the utilities and encouraged
construction of new generation not owned by the utility,
dramatically increasing the number of interfaces. Restructuring
has further complicated the number and types of interfaces.
Today's complicated interfaces
have power going both ways, as is possible
horizontally between two vertically integrated utilities.
Historically, engineers did not have to worry much about pricing
this flow because of the Old Boy Network that seemed to exist
among the vertically integrated utilities (“I scratch your back
now and you scratch mine later.”) But, increased competition has lessened
electric power industry players'
willingness to join the Old Boy
Network and the spirit of cooperation has faded.
Pricing Power Flows
Payments for this two-way flow of
power can be automated, yielding prices that respond to
reliability issues, such as the real-time imbalance between
supply and demand. Certainly economists support the concept of
pricing based on supply and demand, but engineers can analyze
the imbalances' effects so that they may be factored into the
automated pricing mechanism. The Wide Open Load Following (WOLF)
concept is one such pricing plan. (1)(2)(3)
Supplying Needed Reactive
Power
In many respects, reactive power
is the ultimate two-way flow of electricity. Reactive power
flows in and out of an interconnection during each cycle. More
importantly, any customer can be a consumer or a provider
of reactive power, just as any generator can be a provider or a
consumer. Indeed, many parts of the electric network can
both use or consume reactive power, depending on loading at
various times of the day.
The August 2003 blackout
raised the national consciousness of the importance of reactive
power, indeed of its existence. The absence of real-time pricing
of reactive power was a key contributor to the blackout.4
As noted in an earlier column in Today’s Engineer, “Merchant
generators don’t get paid for [reactive power], so they don’t want to supply
it.”5 So, the question is: how do we pay merchant
generators for reactive power?
What should engineers do? They can evaluate whether a particular reactive flow is
good or bad. The terms good or bad indicate whether the flow is
pushing the local voltage toward or away from nominal levels. In
other words, at the retail level, customers with lagging power
factors during low voltage conditions are bad, while customers
with leading power factors are good. Conversely, at the
retail level, customers with lagging power
factors during high voltage conditions are good, while customers
with leading power factors are bad.
That a lagging power factor is not
always bad and that a leading power factor is not always good
was a lesson this author learned 35 years ago during a summer job at
Kentucky Power Company (KPC). KPC used load research to support
its power factor tariff. The power factor tariff encouraged
large industrial consumers to install capacitors which were
sometimes “accidentally” left on during low-load conditions,
leading to bad reactive power flows. The
resulting over-voltage on KPC lines forced KPC to send linemen
out to find the offending customer and ask for the offending
capacitors to be switched off.
The WOLF approach to pricing
begins with quantifying the quality of a public good related to
the commodity to be priced. For reactive power, the public good
is the local electric potential, or voltage, since reactive
power will change the quality of the electric potential. That
is, reactive power will increase or decrease local voltage. The
concept is demonstrated in Figure 1. The horizontal axis is
local voltage. The vertical axis is the rate paid and charged
for reactive power. At the intersection, where the voltage is at
its nominal value, the price for reactive power is zero.

Commodity Pricing
By pricing unscheduled power
flows as commodities, WOLF eliminates the need for such
draconian issues as mandatory reliability standards and
penalties for non-compliance. India has already started pricing
unscheduled power flows as commodities. As a result, India has
improved at least one important reliability index, the variance
of frequency from its standard value of 50 Hertz, by a factor of
ten.6
In short, engineers need to be
able to explain reliability issues to accountants and regulators
in ways that will allow them to implement better
mechanisms for pricing unscheduled flows of electricity. Better mechanisms for pricing unscheduled flows of electricity
can improve network reliability, as it has in India.
References
- "Tie Riding
Freeloaders — The True Impediment to Transmission Access,"
by Mark Lively, Public Utilities Fortnightly, 21
December 1989
- "Parallel
Path Flow Profiteering — Is It Justification for Ending the
Free Lunch on Unscheduled Power Flows?" a presentation by
Mark Lively to Mid-Continent Area Power Pool Fall Operating
Committee Meeting, Brainerd, Minn., 29-31 August 1990;
and, Southeastern Electric Reliability Council Fall
Operating Conference, Asheville, N.C., 10-11 October 1990
-
“Profit-Enhancing Seam Management: A White Paper on Pricing
the Unscheduled Flows of Electricity Across the Seams
Between Utilities Using a Geographically Differentiated
Auction of Inadvertent Interchange,” Released by Mark Lively,
25 March 2001,
www.LivelyUtility.com
- “Power
Crisis: Revenue Accounting Needed: An Issue Paper on the
U.S. Northeastern Blackout, 14 August 2003,” by Mark Lively,
Energy Pulse,
www.energypulse.net/centers/article/article_display.cfm?a_id=521,
28 October 2003
- “Electric
Power Transmission Reliability Not Keeping Pace with
Conservation Efforts,” IEEE-USA Today’s Engineer,
February 2005,
www.todaysengineer.org/2005/Feb/reliability.asp
- “Sidebar on
Reliability Improvement Associated with India Implementing a
Formulary Auction for Unscheduled Interchange,” by Mark
Lively,
www.LivelyUtility.com

Mark B. Lively is a utility
economic engineer who engineers economic solutions for
utilities, and a member of IEEE-USA's Energy Policy Committee in
IEEE-USA.
Comments may
be submitted to
todaysengineer@ieee.org. Opinions expressed are the
author's.
|